Field Progress Tracking
Monitor and update the physical completion percentage for each RAB item.
Project Completion
Weighted average based on item values
23.9%
Overall Progress
Work Items Progress
View Full RABOriginal RAB Items
Pekerjaan Persiapan
Multiplek 18mm Meranti
40 Lembar
Item Progress30.0%
Pekerjaan Pasangan & Plesteran
Kaca Tempered 8mm
15 M2
Item Progress33.3%
Pekerjaan Elektrikal
Lampu Track Light LED
20 Set
Item Progress1.0%
Recent Activity Reports
Lampu Track Light LED
1%
"pasang lampu"
Reported by AdministratorMandor: Ujang29 Apr, 08.53
Kaca Tempered 8mm
33.33%
Volume: 5 M2
"Badai tetap kerja"
Reported by Administrator29 Apr, 08.46
Multiplek 18mm Meranti
30%
"sudah dikerjakan"
Reported by Administrator29 Apr, 08.37
Multiplek 18mm Meranti
25%
Reported by Administrator29 Apr, 08.37