REALIZATION VS ESTIMATE REPORT

Project: Interior Cafe Kopi Kekinian

Date: 28/4/2026
Status: PLANNING
Total Estimate (RAB)
Rp 28.150.000
Total Realized (Actual)
Rp 1.400.000
Overall Variance
+ Rp 26.750.000
NoDescriptionQtyUnitUnit PriceEst. TotalRealizedVariance
Pekerjaan Persiapan
1
Multiplek 18mm Meranti
40Lembar285.00011.400.0001.400.00010.000.000
Pekerjaan Pasangan & Plesteran
1
Kaca Tempered 8mm
15M2650.0009.750.000--
Pekerjaan Elektrikal
1
Lampu Track Light LED
20Set350.0007.000.000--
GRAND TOTAL28.150.0001.400.00026.750.000

Approved by,

Project Manager